Executive summary
- Two rulebooks apply, and IFAD's prevails where they conflict. AVDP procures under the IFAD Project Procurement Guidelines; Sierra Leone's Public Procurement Act, 2016 governs everything they do not cover.
- Register with the NPPA before you bid. Unregistered bidders can be barred, and registration is now online only.
- A complete, on-time bid is the bidder's responsibility. Use the forms as given, include every document asked for, and submit before the closing time: late bids are never accepted.
- Award decisions can be challenged, within strict time limits. 14 calendar days to complain to the PMU, then 10 working days to go to the Independent Procurement Review Panel. Fraud and corruption go straight to IFAD.
1
Two rulebooks apply, and IFAD's rules prevail where they conflict with national law
Section 1(2) of the Public Procurement Act provides that where a funding agency's mandatory procurement rules conflict with the Act, the funding agency's rules prevail; in all other respects the Act governs.4 For AVDP, financed through IFAD, that makes the IFAD Guidelines the primary rulebook.
| IFAD | Government of Sierra Leone | |
|---|---|---|
| Rules | Project Procurement Guidelines1 and Procurement Handbook2 | Public Procurement Act, 20164 and Regulations, 20205 |
| Governs | Methods, bidding documents, evaluation, IFAD review of larger contracts | Supplier registration, complaints and review, award notification, anything IFAD does not cover |
| Oversight | IFAD, including its Office of Audit and Oversight and Sanctions Committee3 | National Public Procurement Authority; Independent Procurement Review Panel7 |
| Integrity | Zero tolerance for fraud and corruption; sexual harassment, exploitation and abuse clauses in every bidding document and contract | Bidders' conduct regulated by the Act and Regulations |
| For you | Follow the bidding document exactly; it applies IFAD's rules | Hold valid NPPA, NRA and NASSIT papers; use the national complaints route |
Source: Public Procurement Act, 2016, s.1(2); IFAD Project Procurement Guidelines and Handbook; IFAD anticorruption policy.
The bidding document for each tender is the final word. Where this guide and a bidding document differ, follow the bidding document.
2
Bidding takes nine steps: the first five are yours, the last four are AVDP's
Most of the outcome is decided before the closing date: a bid that is registered, complete and on time is a bid that can be evaluated.
| Step | Who | What happens | Rule or time limit |
|---|---|---|---|
| 1Register with the NPPA | Bidder | Register online on the NPPA e-GP portal with PDF copies of your Corporate Affairs certificate, NRA tax clearance, NASSIT clearance and, where it applies, council licence. | Unregistered bidders can be barred unless the bidding document says otherwise (s.21(9)).4 Online since 5 Jan 2026.7 |
| 2Find the notice | Bidder | Read the notice on the procurement page: who may bid, bid security, closing date and time. Email alerts announce each one. | Every notice carries a reference number and closing date. |
| 3Get the bidding document | Bidder | Download it from the notice. Read the Instructions to Bidders, the Bid Data Sheet and the qualification criteria in full. | Where a fee applies, the notice says how to pay it. |
| 4Ask questions in writing | Bidder | Email questions before the deadline for questions, quoting the reference number. Answers, addenda and extensions are published on the notice page. | Only written answers change the bidding document. |
| 5Prepare and submit a complete bid | Bidder | Use the forms as given, price every item, include every document on the checklist, and submit through the link or to the address in the notice. | Late bids are never accepted. AVDP bid security: a bank guarantee; no community or village bank security, no insurance bonds. |
| 6Open the bids | AVDP | Bids are opened in public or by video call at the time in the notice. Bidder names and prices are read out and recorded. | Bidders or their representatives may attend. |
| 7Evaluate | AVDP | A committee checks each bid against the bidding document's criteria only. Goods and works go to the lowest evaluated bid that meets all requirements from a qualified bidder. | Do not contact the committee during evaluation. IFAD reviews larger contracts before award.2 |
| 8Notify the award | AVDP | All bidders are told of the proposed award at the same time; unsuccessful bidders are told why and can ask for a debriefing. | No contract signature for at least 14 calendar days (s.56(3)); reasons given (s.27).4 |
| 9Sign and publish | AVDP | The contract is signed after the waiting period and any complaint is resolved, and the award is published on the contract awards page. | No signature while a complaint is pending (s.56(5)).4 |
Source: Public Procurement Act, 2016, ss.21, 27 and 56; NPPA Circular 02/2025; IFAD Project Procurement Handbook; AVDP invitations for bids, 2023 to 2026.
3
A missing document can make a bid non-responsive: check every item before you submit
What AVDP notices usually ask for. The list in your own bidding document is the one that counts: it may ask for more, or for less.
Bidders registered in Sierra Leone
- Business registration certificate (Corporate Affairs Commission)
- Valid NRA tax clearance certificate
- Valid NASSIT clearance certificate
- Valid local council licence
- NPPA supplier registration
Bidders registered abroad
- Certificate of incorporation or registration
- Valid tax clearance from the home country
Every bid
- Bid security in the form and amount asked for, usually a bank guarantee
- Signed bid submission form and price schedules, on the forms provided
- Signed declarations on fraud and corruption, and on sexual harassment, exploitation and abuse, where included
- Evidence of qualification: similar contracts, financial statements, equipment, key staff
- Power of attorney for the signatory, where asked
- Submitted through the link or to the address in the notice, before the closing time
Source: AVDP invitations for bids and requests for quotations, 2023 to 2026; NPPA Circular 02/2025.
4
Decisions can be challenged, but only within strict time limits
A bidder who has suffered, or may suffer, loss can seek review at any stage before the contract comes into force.4 Fraud and corruption follow a separate route, to IFAD.
- Within 14 calendar days
Complain in writing to the PMU
From when you became, or should have become, aware of the problem (s.64(2)). Send it to contact@avdp.org.sl with the notice reference.
- Within 5 working days
The PMU decides in writing
The head of the procuring entity must issue a written decision (s.64(3)).
- Within 10 working days
Apply to the Independent Procurement Review Panel
If there is no decision in time, or you disagree with it (s.64(4) and (5)). The contract cannot be signed while the complaint is pending (s.56(5)).
Report fraud or corruption to IFAD
Bribery, fraud, collusion, coercion or obstruction in an IFAD-financed project: anticorruption@ifad.org or +39 06 5459 2888. Reports can be anonymous, and firms found to have engaged in these practices can be sanctioned by IFAD's Sanctions Committee.3
Source: Public Procurement Act, 2016, ss.56, 63 and 64; IFAD anticorruption policy.
You can also use the Report a concern form on this site, without giving your name.
Sources
- IFAD Project Procurement Guidelines
- IFAD Project Procurement Handbook
- IFAD anticorruption policy and reporting
- Public Procurement Act, 2016 (Act No. 1 of 2016)
- Public Procurement Regulations, 2020
- NPPA e-GP supplier registration portal
- National Public Procurement Authority
The Public Procurement Act is under review in 2026; check the NPPA for changes. Section numbers refer to the Act as published on 25 February 2016. Last checked November 2026.